Monday, December 22, 2008
Kids are in their new bedrooms
We started moving stuff into the new rooms now. The kids are in their new bedrooms. The new bathroom is being used, and the bulk of the living room furniture is in the new livingroom. Still have plenty more to rearrange, but at least we can finally start using the new space in the house.
Carpeting is done
Carpets are done in the house. We went with Mohawk brand, SmartStrand. They are corn-based threads, which are better for the environment, naturally stain-resistant, and naturally very soft. All the floors upstairs are the same grey color. That way, it won't clash with any paint we use in the future. Downstairs is a pale tan color.
Septic system is in
Thursday, December 4, 2008
More inspector delays....
We need inspections for the septic system, so the excavator doesn't want to start digging the hole until Monday....
Most of the inside plumbing is done, at least. Just the final connection to the new waste pipe (can't do it yet, since the new pipe doesn't go anywhere.... :) )
Most of the inside plumbing is done, at least. Just the final connection to the new waste pipe (can't do it yet, since the new pipe doesn't go anywhere.... :) )
Friday, November 21, 2008
Stair railing is done
They finished assembling the stair railing yesterday. It looks beautiful. I still have to stain and seal it, but I want to test out the colors on some scrap wood first.
Thursday, November 20, 2008
We have heat!
Wednesday, November 19, 2008
Color on the walls
Monday, November 17, 2008
Bamboo floor
The office has bamboo flooring from Teragren www.teragren.com/
It has no formaldehyde, and it is responsibly grown and harvested. It's also a very hard "wood".
It has no formaldehyde, and it is responsibly grown and harvested. It's also a very hard "wood".
All the walls are primed
The painter made quick work of painting. All the walls are primed, and the ceilings are done in the final coat. Now it's really starting to look finished. The walls are solid now. Yes, it's all a very boring white, but at least it's a solid white.
The paint is ZERO VOC paint from MythicPaint http://www.mythicpaint.com/
There is no smell to the paint, no poisonous chemicals off-gassing, much better for the environment, etc.
The paint is ZERO VOC paint from MythicPaint http://www.mythicpaint.com/
There is no smell to the paint, no poisonous chemicals off-gassing, much better for the environment, etc.
Thursday, November 13, 2008
Spackle is done
They finally came yesterday to finish the spackling. We're still not sure why they didn't come for a few days.?.? Anyway, they are done. There's that delightful white dust all over the downstairs..... Luckily, upstairs we were able to tarp off the existing part of the house, but downstairs is too open, and too much stuff there to protect it. When we move everything to the new part of the house, we'll just have to clean it piece by piece.
Tuesday, November 11, 2008
Upstairs doors are in and windows framed
Friday, November 7, 2008
Spackle is going on
The first coat of spackle is up. It takes a while to dry, so there is one day when it just sits there.... They are coming back on Saturday to do the 2nd coat. That gives it Sunday to dry, then Monday they can finish. Next week should be really fun. That's when a lot of the finish work starts happening.... :)
Tuesday, November 4, 2008
Drywall going up
The drywall is done downstairs, and most of it is done upstairs. They should be done by today, or tomorrow at the latest. The drywall really starts to make the rooms look like rooms. Once the spackler comes in and does his thing to make the walls look like one solid wall, instead of pieces of drywall screwed to the wall, I think it will make another huge transition towards being "done".
Wednesday, October 29, 2008
Inspection completed, insulation installed
The inspector came and OKd everything. The same day, the insulators finished insulating the entire house. Warmth is nice.... :)
We insulated all of the interior walls and ceiling as well to sound-proof the rooms a bit. That way, nobody is bothering anybody else if they are making noise in one room, and the other room needs to be quiet.
We insulated all of the interior walls and ceiling as well to sound-proof the rooms a bit. That way, nobody is bothering anybody else if they are making noise in one room, and the other room needs to be quiet.
Friday, October 24, 2008
Inspector called in sick....
We were scheduled to have the plumbing and HVAC inspection today.... he called in sick.... now we have to go until Monday until we can find out when we *might* get an inspection. It's getting cold and we need insulation, but we can't insulate until the inspection.....
The Town is always the biggest hurdle with every phase of this project.....
The Town is always the biggest hurdle with every phase of this project.....
Tuesday, October 21, 2008
Front deck and railings are done
Wednesday, October 15, 2008
Gutters are on
Gutters went on today. The outside is just about done. They just have to finish the front porch.
Tuesday, October 14, 2008
Siding is up
Friday, October 10, 2008
Stonework is done
They finished laying the stone for the front foyer. It looks awesome. I'm definitely glad we decided to add that feature. It makes a big difference in the look of the house.
The stone is made in forms using a type of concrete material. It looks like real stone, but it's lighter, easier to work with, and cheaper than real stone. Once it's up, you can't tell the difference.
The stone is made in forms using a type of concrete material. It looks like real stone, but it's lighter, easier to work with, and cheaper than real stone. Once it's up, you can't tell the difference.
Saturday, October 4, 2008
It's not supposed to be this cold yet!
The weather is unusually cold right now. Unfortunately, half the house isn't insulated, so it doesn't make any sense to even try turning the heat on..... Hopefully the cold snap will end soon, and the insulation will go in in about a week or so....
Thursday, October 2, 2008
Preliminary wiring for solar panels
The solar panel installer is over today running the preliminary wiring from the roof to the basement. If he runs it when the house has no insulation or drywall, he can run everything inside the wall, and it will look much cleaner and more professional. The latest ETA on the panels showing up is January some time.....
Friday, September 26, 2008
Passed framing and strapping inspection
No pictures for this post, but we passed the building inspection for the framing and strapping. That means we can start covering the walls up with siding and insulation.
Wednesday, September 24, 2008
Most of downstairs windows are in
All of the downstairs windows are in except for the bay window. Since they are installing a new window directly over the bay, they decided to do the 2nd floor window first. The bay window area is all framed, though, so it should be a relatively simple process to put it in (Heavy process, but simple.... :) )
We have use of the front door again!
We have use of the front door again!
Tuesday, September 23, 2008
Windows are going in
Monday, September 22, 2008
Roof shingles are on
Front door is in
They installed the front doors and transom window. The foyer is still closed off to the old part of the house, so we aren't using the doors yet, but at least we can see what they look like. I was worried about them looking too big, since they are double doors, but with how wide the house is, the scale is perfect.
Wednesday, September 17, 2008
No front door!
Monday, September 15, 2008
Roof is framed
Thursday, September 11, 2008
2nd floor framed