Saturday, October 4, 2008
It's not supposed to be this cold yet!
The weather is unusually cold right now. Unfortunately, half the house isn't insulated, so it doesn't make any sense to even try turning the heat on..... Hopefully the cold snap will end soon, and the insulation will go in in about a week or so....
Thursday, October 2, 2008
Preliminary wiring for solar panels
The solar panel installer is over today running the preliminary wiring from the roof to the basement. If he runs it when the house has no insulation or drywall, he can run everything inside the wall, and it will look much cleaner and more professional. The latest ETA on the panels showing up is January some time.....
Friday, September 26, 2008
Passed framing and strapping inspection
No pictures for this post, but we passed the building inspection for the framing and strapping. That means we can start covering the walls up with siding and insulation.
Wednesday, September 24, 2008
Most of downstairs windows are in
All of the downstairs windows are in except for the bay window. Since they are installing a new window directly over the bay, they decided to do the 2nd floor window first. The bay window area is all framed, though, so it should be a relatively simple process to put it in (Heavy process, but simple.... :) )
We have use of the front door again!
We have use of the front door again!

Tuesday, September 23, 2008
Windows are going in
Monday, September 22, 2008
Roof shingles are on
Front door is in
They installed the front doors and transom window. The foyer is still closed off to the old part of the house, so we aren't using the doors yet, but at least we can see what they look like. I was worried about them looking too big, since they are double doors, but with how wide the house is, the scale is perfect.





Wednesday, September 17, 2008
No front door!
Monday, September 15, 2008
Roof is framed
Thursday, September 11, 2008
2nd floor framed